    Fitting Mode:>>PE sleeve joint
     ·Construction period short
     ·Construction simplify
     ·Construction cost cheaper( insulated form: PUR)

 
1、Abrade the edges of the oversized casing And the area of PE-jacket to be covered. Remove all abrasion dust accurately.
2、Use torch preheat the joint to be covered.
3、Make Dual Seal wrap centering the sleeve,Assemble the patch in the center of the overlap.
4、Start shrinking from the middle of joint.
5、Gently press the sleeve, The small wrinkle Will disappear to form a smooth surface.
6、Inspect the finished joint for Dual Seal affixed fastness and smooth.

Sales Address:A Dong 6005,Hetaiyunheng B/D., No.109 nanjing BeiSt., Heping District Shenyang Liaoning china
Tel:024-82901890,82901891,82901892
Fax:024-82901895
Zip:110002
Web:http://www.sygooweol.com
   Factory Address:Xiaoyangan Village Baita Town Dongling District Shenyang Liaoning China
  Tel:024-23787480
  Fax:024-23787467
  Zip:110167
  E-mail:gooweol@163.com